MEXICO / DIGITAL INFRASTRUCTURE / ELECTRICITY

CloudHQ Querétaro: what is earlier usable capacity actually worth?

A named Mexican data-centre project, a public capacity discrepancy, and a probability-weighted commissioning decision.

RESEARCH DEMONSTRATION — NOT A CLIENT CASE STUDY · Evidence reviewed:

Headline megawatts are not contracted revenue. The commercial question is whether an earlier energization path creates enough risk-adjusted operating value to pay for its incremental execution cost.

Verified public evidence

CloudHQ’s QRO campus page describes six buildings of 48 MW of IT load each, yet separately lists 360 MW of critical IT load. Six times 48 MW equals 288 MW; the unreconciled 72 MW (25% of 288 MW) is a due-diligence question about design, phasing, or definition—not an accusation that the company is wrong.

The same company page specifies a 400 kV onsite substation and a ready-for-service target within 2027. Voltage in kV, electrical capacity in MVA/MW, contracted IT load in MW, energized capacity and occupied billable kW are different metrics. They must not be added, equated, or substituted into a revenue model.

Mexico announced a US$4.8bn six-building project in September 2025. This is an investment announcement, not evidence of capital spent. A September 2026 news report attributes to CloudHQ’s local executive a completed first 400 kV substation and a second substation at 36% progress. This account does not establish a commissioned energization date or signed customer contracts.

For context, a separate developer, ODATA, described energization at its own Querétaro campus in 2025. This is a useful reminder of the difference between energized and planned capacity, not a like-for-like project valuation or proof of CloudHQ schedule risk.

MetricValueStatus
CloudHQ publicly described buildings6 × 48 MW IT load = 288 MWCompany-described design; arithmetic derived; NOT commissioned capacity
CloudHQ displayed critical IT-load total360 MWCompany-listed capacity; differs from six-building sum by 72 MW; reconciliation required
CloudHQ site power-supply description400 kV onsite substation; RFS within 2027Company-stated voltage and readiness target; neither is a confirmed energized MW figure
Government announced project investmentUS$4.8 billion; 6 data centresSep 2025 announcement, not verified spending / signed supply orders
Substation build-progress accountFirst reportedly complete; second 36% as of Sep 2026Attributed to company executive by secondary press; energization and utility acceptance not demonstrated
Government-scope announcement / attributed executive expansion~900 MW (2025), up to 920 MW (reported Sep 2026)Broader contemplated power/project envelope; not directly comparable to 288/360 MW IT figures or commissioned load
Reported phase-one power arrangements200 MW (reported scope, 2025)Agreement/secured power as reported; not proof that 200 MW was accepted/energized or leased
September 2025 company deck — preliminary computing loadUp to 600 MW critical computing loadPresentation ambition, not reconciled to site 288 or 360 MW, or 900 MW later description
October 2026 financing / associated power updateNearly US$6bn financing and near 1,000 MW energy capacityReported revised contemplated project scope, not verified disbursement, grid-connected load or signed procurement
Corporate 2025 presentation computing-load scenarioUp to 600 MW critical computing loadCompany-branded presentation reproduced externally; potential scope differs from current webpage
Corporate 2025 presentation electrical capacityInitial 200 MW of proposed 900 MW campus electricity requirementInitially secured arrangement is not energized billable IT capacity
Corporate 2025 switching stationProposed 2 GW for campus and regional gridSwitching infrastructure is NOT 2 GW sellable data-center IT capacity
October 2026 revised project-scale reportingNearly US$6bn proposed and close to 1,000 MW energy capacitySecondary reporting of company/state meeting; neither incurred cash nor delivered megawatts verified

Commercial consequence

Use the publicly described 48 MW building only as a SCALE anchor. Suppose 65% of its critical IT load becomes occupied, contracted and billable at an incremental operating contribution of US$70 per occupied kW-month for 120 operating months. Model a three-month commissioning shift with unchanged operating life and unchanged baseline capital expenditure. Convert a 12% effective annual discount rate into an effective monthly rate. Neither utilization, contracts, margins, 120-month life, 3-month opportunity, discount rate, 40% success probability nor US$750k acceleration expense is public project data.

The illustrative 48 MW module contributes US$2.184 million per operating month and loses US$4.359 million of present value if the same 120 monthly contributions start three months later. The US$6.552 million nominal value of three months of contribution is NOT the loss in the same-life shifted schedule. With only a hypothetical 40% chance that an extra US$750,000 of mitigation achieves the improvement, incremental expected pre-tax NPV is about US$0.994 million. A break-even probability of roughly 17.2% marks when the additional cost is justified in this simplified comparison.

Modeled decision economics

Illustration, not actual client return

Assumptions (illustrative, not observed)

Reference IT module48 MW
Occupied and billed proportion65%
Operating contributionUS$ 70/kW/month
Operating period120 months
Discount rate12% effective annual
Schedule shift3 months
Probability of success40%
Additional acceleration expenseUS$ 750,000

Reproducible calculation

C = (48 MW × 1,000 kW/MW) × u × c. rₘ = (1 + 0.12)^(1/12) − 1. PV₀ = Σ(t=1..120) C/(1+rₘ)^t. PV₃ = PV₀/(1+rₘ)^3. ΔPV = PV₀ − PV₃. Expected ΔNPV = P(success) × ΔPV − incremental cost. Break-even P = incremental cost / ΔPV.
Contribution per operating monthUS$ 2,184,000
PV without delayUS$ 156,058,886
PV with three-month shiftUS$ 151,699,446
Value of three months earlier startUS$ 4,359,439
Expected value after extra costUS$ 993,776
Minimum probability for break-even17.20%

Present-value benefit from an earlier start (US$), holding 120-month operating life constant

OccupancyContribution (US$/kW-month)ΔPV
40%US$ 40US$ 1,532,990
40%US$ 70US$ 2,682,732
40%US$ 100US$ 3,832,474
65%US$ 40US$ 2,491,108
65%US$ 70US$ 4,359,439
65%US$ 100US$ 6,227,770
85%US$ 40US$ 3,257,603
85%US$ 70US$ 5,700,805
85%US$ 100US$ 8,144,007

Decision gates before commitment

  1. Capacity reconciliation: obtain an approved IT-load phase schedule reconciling 288 MW and 360 MW; distinguish installed electrical MVA from usable, contracted IT MW.
  2. Grid access: verify utility energization, protection studies, 400 kV substation acceptance, firm delivery, rights-of-way and commissioning dependencies before changing dates.
  3. Customer economics: examine signed lease/start-of-billing dates, ramp, reserved kW, discounts, contracted term, power pass-through, uptime penalties and cash contribution.
  4. Commercial execution: collect binding EPC/OEM quotations and critical-path evidence for acceleration alternatives; calculate probability of success from comparable historical projects.
  5. Decision rule: accelerate only if risk-adjusted incremental NPV remains positive after capex timing, tax, FX, financing, interruption costs and downside stress tests.

Scope and limitations

An independent project-economics demonstration, not a customer engagement, CloudHQ earnings estimate or proposal. All occupancy, contribution, project duration, delay-reduction feasibility, probability and extra spend are scenario parameters requiring contract and engineering confirmation. The published MW figures use different and unresolved technical/project definitions.

How the analysis becomes client value

LARGITAS would turn this screen into a board-ready decision by reconciling capacity, validating customer economics and procurement milestones, reconstructing a monthly unlevered cash-flow model, separately evaluating accelerated spending and contractual penalties, and delivering go/hold/renegotiate thresholds. Research may support an acceleration, a revised commercial offer, or a decision not to invest.

01 — Investment question and decision thesis

The commercial question is not whether a very large data-center development has been announced. It is whether a defined increment of electrically accepted, connected, commissioned and contracted capacity can produce distributable operating contribution earlier, and whether the incremental expenditure needed to change the critical path has positive risk-adjusted value. An announcement, a building shell, substation voltage, line rating, available power, IT load, customer commitment and invoiceable capacity describe different stages of value creation.

For LARGITAS, this creates two distinct potential assignments: a developer-side commissioning and capital-sequencing decision, and a supplier-side opportunity-qualification decision. The former should be evaluated with incremental discounted cash flow; the latter with addressable scope, bid probability, avoidable costs, timing and counterparty exposure. Neither is substantiated by multiplying announced megawatts by a guessed rental tariff.

02 — Chronology: what changed and when

  • September 2025: CloudHQ's project presentation describes six planned data centers, up to 600 MW of critical computing load, initial power arrangements for the first 200 MW of a 900 MW campus electrical requirement, more than US$250 million of estimated predevelopment capital, US$4.8 billion of planned construction, a private campus substation up to 900 MW, and a 2 GW switching station supporting the wider grid. The 2027 dates are plans, not operational certifications. [S1]
  • September 25, 2025: Mexico's federal government announces US$4.8 billion for six facilities on 52 hectares, and projected construction and permanent jobs. This is a public announcement rather than audited capital deployed. [S2]
  • The corporate QRO campus webpage, accessed October 23, 2026, displays 360 MW of available/total critical IT load and describes six buildings of 48 MW IT each (288 MW arithmetically). It also gives 254,400 square meters without proving that figure represents the same land parcel as the government's 52 hectares. [S3]
  • September 10, 2026: El Economista attributes to a CloudHQ executive a completed first 400 kV substation, 36% progress on another, roughly two years of land-related preparation, roughly three years linked to energy development and discussion of up to 920 MW. These are attributed remarks, not independent certificates of energization. [S4]
  • October 5–13, 2026: local reporting, quoting an updated company/state meeting, describes a proposed increase from US$4.8 billion to nearly US$6 billion and nearly 1,000 MW of energy capacity. This is a later project-scope report. It cannot be treated as cumulative cash invested or as a completed capacity increase. [S5]

Commercial-contract status control: The September 2025 company presentation says that, following initial power arrangements, CloudHQ intended to secure a long-term lease with a leading global technology company and proceed with construction. That statement is evidence of a planned contractual milestone at the document date, not evidence that no lease has since been signed. A tenant-specific billing date and its actual status must be independently established before treating additional usable MW as cash-generating capacity. [S1]

03 — Capacity reconciliation: the foundational control

Public figureExact meaning disclosedTreatment in analysis
6 × 48 MW = 288 MWSum of six IT load figures on corporate webpageDesigned-building reference, not proof of commissioned power
360 MWCritical IT load stated elsewhere on same webpageDistinct corporate headline requiring reconciliation
Up to 600 MWCritical computing load in September 2025 presentationDifferent potential stage/scope than 288 or 360
First 200 MWInitial power reportedly secured in September 2025Supply arrangements, not proof of accepted energization
900 MWStated campus electricity load/private substation designElectrical scope, not necessarily critical IT load
Up to 920 MWPotential scale attributed in September 2026 reportingVerbal outlook, not certified installed power
2 GWSwitching station proposed to support regional grid and campusGrid asset scale; must not be treated as 2 GW of sellable campus IT
400 kVVoltage class of substation/transmission interfaceVoltage, NOT 400 MW or 400 MVA

MW is active power, MVA is apparent power and kV is voltage. The conversion between MW and MVA needs power factor; the relation between facility electrical draw and IT load requires an explicit power-usage-effectiveness (PUE) definition, auxiliary consumption and relevant operating window. A simple ratio such as 900/600 = 1.5 is not proof of PUE because both numerators and denominators may describe different development phases or infrastructure boundaries. Actual net deliverability also depends on accepted interconnection, transformer ratings, redundancy, grid availability, customer provisioning and operating permits.

An additional primary-source terminology issue exists: the September 25, 2025 federal conference transcript verbally refers to roughly 900 MW of “critical computing load,” whereas the branded presentation distinguishes up to 600 MW of computing load from 900 MW of campus electrical load. This difference should be flagged as a possible spoken-definition or scope inconsistency, not silently resolved or alleged to be misconduct. [S8]

04 — Land, site footprint and construction status

The presentation and federal release describe 52 hectares. The corporate webpage lists 254,400 square meters, approximately 25.44 hectares, but its label is embedded in a campus-property description with a square-foot equivalent. That could be building area, a distinct parcel, phased floor area or another measurement. It must not be described as a verified land-boundary contradiction without survey documents. The correct diligence request is an indexed site master plan, property title schedule, cadastral polygons, building area program and phase-by-phase permits.

Public claims about substations being 'complete' have similarly narrow meanings. Civil completion, installed equipment, commissioning tests, utility acceptance, first energization, load-testing, firm power quality and redundant operation are separate milestones. The cash-flow model should begin only after the contractually defined service-availability or invoicing milestone, not merely after civil completion.

05 — Sector and grid context

Proyectos México reports 2025 electricity generation of 353,820 GWh, a 52,945 MW peak in the National Interconnected System, 111,195 km of transmission and 908,195 km of distribution, with approximately 49.8 million users. The national totals establish system scale, not spare capacity at CloudHQ's connection node. [S6]

Mexico's published electricity planning materials describe a Querétaro supply project, P24-OC3, and timing, transformation and transmission constraints. Secondary reporting attributes to the plan 675 MVA of transformation and 51.2 circuit-km. These figures should not be asserted as dedicated CloudHQ power without interconnection and ownership documents. [S7]

Regional electricity generation sufficiency is not sufficient evidence of substation-level deliverability. A data center can be delayed by right-of-way, utility interface, transformer supply, protection studies, fiber route diversity, water/cooling permits, traffic or tenant contract execution even when generation exists elsewhere.

06 — Decision unit and boundary of the model

Use ONE company-described 48 MW IT-load building as an analytical unit, strictly as a scale reference. Its modeled 65% billed/occupied utilization, US$70 per billed kW-month contribution margin, 120-month operating life, 12% effective annual discount rate and three-month service-start difference are assumptions, not CloudHQ operational data. The modeled US$70 is contribution after modeled variable costs, NOT gross rent, EBITDA, net profit or actual CloudHQ pricing. The 120-month economic life is held constant for the two alternatives to isolate timing rather than delete three months of operations.

The result is an incremental operating cash-flow timing experiment. It deliberately excludes construction draw timing, inflation, taxes, debt service, terminal value, vacancy ramp shape, tenant rebates, penalties, decommissioning and possible contract-end-date effects. In a real mandate these belong in a linked, project-specific financial model.

07 — Exact mathematics: three-month change in service date

  • IT capacity reference: K = 48 × 1,000 = 48,000 kW.
  • Hypothetical paid proportion: u = 0.65. Contribution margin: c = US$70 per billed kW-month.
  • Monthly incremental operating contribution: C = K × u × c = US$2,184,000.
  • Monthly discount factor: i = (1 + 0.12)^(1/12) − 1 = approximately 0.9488793%.
  • On-time annuity value: PV0 = Σ(t=1..120) C/(1+i)^t = approximately US$156,058,886.
  • Same 120 cash flows beginning three months later: PV3 = PV0/(1+i)^3.
  • Value of advancing this hypothetical schedule: ΔPV = PV0 − PV3 = approximately US$4,359,439.
  • Assuming 40% incremental probability the proposed intervention succeeds and US$750,000 paid regardless: expected incremental NPV = 0.40 × ΔPV − 750,000 = approximately US$993,776.
  • Success probability needed to break even: p* = 750,000/4,359,439 = 17.20%.

The value is mathematically attributable to the timing of contribution, not automatic 'revenue recovered.' The intervention cannot produce these economics unless it actually improves the binding completion path and the capacity is paid for. If the contract has a fixed expiry rather than a fixed operating tenure, the delayed case must separately remove terminal cash flows; this model intentionally does not.

08 — Sensitivity and loss-producing alternatives

Billed occupancyContribution US$/kW-monthValue of 3-month accelerationEV at 40% success less US$750k
40%40US$1.533m−US$0.137m
40%70US$2.683m+US$0.323m
65%70US$4.359m+US$0.994m
85%100US$8.144m+US$2.508m

At only one month of actual schedule acceleration, the base contribution case gives approximately US$1.467m in timing value, and the same 40%-success/US$750k intervention has negative expected NPV of approximately US$163k. Six months would generate more timing value, but cannot be assumed unless the critical-path analysis supports six months. The model therefore rejects expensive schedule remedies when expected benefits do not justify them.

In project-specific work, build a three-way scenario surface over commissioned MW, contracted occupancy and schedule months; add a probability distribution for approvals, supply constraints and commissioning outcomes, then reconcile developer and tenant economics to avoid double counting.

09 — Vendor-side commercial opportunity map

A very large construction budget is a procurement context, not a sales pipeline. The qualifying chain is: defined project package → package owner and contracting party → confirmed technical requirement → tender/procurement method → procurement timing → eligibility → deliverable supplier capability → competition and price → financed execution → awarded order. Only then can a potential opportunity enter an expected-contribution model.

Relevant categories may include transformers and high-voltage equipment, protection relays, switchgear, optical fiber and physically diverse routes, cooling systems, industrial controls, power quality monitoring and commissioning services. Presence on this list does not establish a planned tender for any particular supplier, an available contract amount or an introduction to CloudHQ.

10 — Counterparty, operating and regulatory diligence

  • Capacity: establish which MW are IT, facility input, import entitlement, contracted supply, tested demand and reserved electrical headroom.
  • Commissioning: dated acceptance requirements; utility and customer test protocols; redundancy class; energized assets; fault-ride-through and protection coordination.
  • Customers: executed lease or service agreement, initial billing trigger, ramp schedule, take-or-pay provisions, credits, termination rights and counterparty credit strength.
  • Grid: interconnection agreement, grid-impact studies, queue status, firm/nonfirm conditions, right-of-way and curtailment/quality risks.
  • Costs: vendor quotations, imported component content, FX, logistics, schedule contingencies, insurance, availability penalties and alternative sourcing.
  • Environment: approved site permits and water/cooling specifications; distinguish advertised waterless cooling from independently measured lifetime water consumption.
  • Finance: funding commitments and disbursements, lender conditions precedent, interest during construction, tax treatment and working-capital needs.

11 — Competing hypotheses and attempted falsification

Alternative A: there is no economically material delay because tenants pay only on a fixed later date independent of commissioning. Then early energization creates minimal cash-flow value. Alternative B: available power is not the binding constraint; tenant contracting or telecom backhaul is. Then acceleration spend on substations may have zero incremental effect. Alternative C: apparently inconsistent MW figures are simply phase distinctions. Then the conclusion is reconciliation, not misstatement. Alternative D: market demand supports the campus but phased rollout yields superior return to early scale. A real investment recommendation must test all four against documents before deciding.

12 — Quantifying LARGITAS's potential decision contribution

Deliver a dated capacity ledger, project-critical-path diagram, tender-package registry, supplier qualification matrix, contract-specific financial workbook, 5–95% sensitivity intervals and an executive go/no-go decision memo. The value claim should be expressed only as the result of a decision comparison: NPV of selected alternative minus NPV of defensible baseline after advisory fees and implementation costs. For example, a hypothetical US$0.994m expected value is not a LARGITAS-earned saving, nor a guaranteed client benefit; it is the output of an assumed decision problem.

13 — Failure conditions and next-verification sequence

Reject the acceleration proposal if the targeted bottleneck is not critical, if accepted capacity cannot be billed on the accelerated date, if contractor incentives are misaligned, if probabilities are unsupported or if all-in acceleration costs exceed probability-weighted NPV. Freeze inconsistent capacity figures as unresolved, commission a phase-by-phase reconciliation, obtain the commercial start-condition, then replace assumptions with executed contract and engineering schedule data. No vendor engagement or client relationship is implied by this independent company analysis.

14 — Publication discipline and reference register

[S1] CloudHQ QRO presentation, September 2025, especially page 4: 600 MW computing load, first 200 MW power, up-to-900 MW campus substation, 2 GW switching station and planned US$4.8bn construction (linked in primary sources below).

[S2] Mexican Presidency announcement, September 25, 2025: announced scope, location, investment and jobs. [S3] CloudHQ QRO webpage, accessed October 23, 2026: 360 MW display, six 48 MW descriptions, RFS within 2027 and 400 kV interface. [S4] El Economista, September 10, 2026: attributed executive remarks on land, energy and substation progress. [S5] El Economista and Data Center Dynamics, October 2026: reported updated proposed scale. [S6] Proyectos México electricity profile: published 2025 national system metrics. [S7] SENER electricity planning, via official publication and contemporary reporting: Querétaro constraints and proposed grid reinforcement. Figures are dated; announcements are not actuals.

15 — Additional diligence annex: critical-path dependencies

Before paying an acceleration premium, trace four interlocked critical paths independently: property/permits, grid interconnection, mechanical and electrical completion, and commercial tenant acceptance. A shorter equipment delivery schedule has zero financing value if the interconnection agreement or tenant start condition still governs first billing. In a staged campus, record the first building separately from the total campus to prevent capacity and CAPEX double counting.

Electrical definitions and engineering conversions

Apparent power S (MVA) and active power P (MW) are linked by P = S × power factor, within equipment and thermal limits. Facility input energy at one measured time can be approximated by IT consumption × verified instantaneous PUE; annual PUE or commissioning assumptions require their own metering basis. For example, a 100 MVA transformer at 0.95 power factor is nominally associated with 95 MW active power before reserves, derating, redundancies and system constraints; this is a dimensional illustration, NOT the rating of the QRO project. No public MW figure should be promoted to a definitive contracted supply entitlement without utility records.

Scope-change risk and October 2026 project updates

The proposed move from US$4.8bn toward nearly US$6bn in October 2026 is an increase in the reported project funding envelope of approximately US$1.2bn, or 25%, if comparing the two rounded announcements. It is NOT a statement of additional capital already spent, a verified cost overrun, a full financing commitment or additional signed customer demand. The later 'nearly 1,000 MW' refers to energy-infrastructure plans, not proof of 1,000 MW of billable IT. A serious analyst requests the dated change-control register, added scope and revised contract schedule. [S5]

16 — Risk-adjusted acceleration: full scenario grid

OccupancyContribution US$/kW-monthThree-month discounted valueExpected incremental value with 40% success and US$750k cost
40%40US$1.533m−US$0.137m
40%70US$2.683m+US$0.323m
40%100US$3.832m+US$0.783m
65%40US$2.491m+US$0.246m
65%70US$4.359m+US$0.994m
65%100US$6.228m+US$1.741m
85%40US$3.258m+US$0.553m
85%70US$5.701m+US$1.530m
85%100US$8.144m+US$2.508m

The intervention decision is not based on upside alone. P(success) must represent a probability of additional earlier operation caused by the spending, not the overall probability that the campus will someday complete. If commissioning date probabilities are correlated with tenant occupancy or grid congestion, the 3×3 grid alone overstates certainty and a scenario tree or simulation with correlated states is necessary. The displayed values are approximate rounded figures.

17 — Commercial sourcing and verification sequence

The logical sequence for a paid mandate is: freeze factual record at an as-of date; identify contract/electricity boundaries; validate engineering path and customer commencement terms; quantify baseline cash flows; model ranked feasible interventions; stress timing, power, tenant and financing risks; solicit necessary formal quotations with authorization; then report an evidence-weighted go/no-go recommendation. This firm must not imply that it possesses confidential client documents or has secured buyer introductions.

18 — Three-case assumption protocol

The three sets below are boundary tests, not a fitted probability distribution. Use the central reference as the working case and inspect downside/upside; never average scenario outputs without defensible weights.

CaseOccupancyContribution US$/kW-monthAssumed success probabilityIntervention costExpected incremental NPV
Downside40%4020%US$1,250,000US$-943,402
Central reference65%7040%US$750,000US$993,776
Upside85%10060%US$500,000US$4,386,404

Assumption disclosure: the 48 MW public building reference is factual; occupancy, contribution, marginal costs and success probabilities are scenario inputs, not CloudHQ contracts. Values follow the same 120-month annuity / three-month shift method as the central study. These success probabilities are illustrative, so EV is conditional rather than forecast.

Decision rule: report the CENTRAL scenario as the provisional working case and the full range separately. Do not take the mean of three hand-picked cases; use a probability-weighted expectation only when probabilities have an auditable empirical basis.

19 — Documented industry precedent: measured cooling-energy reduction, not a LARGITAS result

The U.S. EPA ENERGY STAR program records a completed 2013 air-side economizer retrofit at Marvell Semiconductor’s 720 kW data center in Santa Clara, California. The publisher lists mean monthly electricity use of 1,361,450 kWh in the preceding 12 months and 1,091,280 kWh in the following 12 months; difference 270,170 kWh/month. Annualized arithmetic at those reported monthly averages is 3,242,040 kWh/year, equivalent to 19.84% of the earlier monthly mean. ENERGY STAR reports US$27,000/month, or US$324,000/year, of savings, US$662,000 installed cost and a US$171,000 utility rebate. Recomputed simple payback: 662,000/324,000 = 2.04 years gross, or (662,000−171,000)/324,000 = 1.52 years after the rebate. [S9]

Attribution boundary: This is an externally documented historical intervention by another organization, not a CloudHQ campus result and not a LARGITAS client outcome. An observed before/after comparison is useful but not the same as a controlled experiment: weather, utilization, load growth and other operations may differ between the twelve-month periods. These numbers illustrate that facility engineering decisions can have quantifiable monetary consequences; no saving should be carried over mechanically to Querétaro without climatic engineering, tariffs, capital pricing, load shape and verified contract terms.

Evidence references

  1. [S1] CloudHQ QRO Campus presentation (branded corporate slides, September 2025, page 4; reproduced by third-party host)
  2. [S2] Presidencia de México / Secretaría de Economía — investment announcement, 25 Sep 2025
  3. [S3] CloudHQ / QRO Campus — company project page, accessed 22 Oct 2026
  4. [S4] El Economista — reporting on CloudHQ executive remarks, 10 Sep 2026
  5. [S5] El Economista — 5 October 2026 CloudHQ scope and financing update
  6. [S6] Proyectos México — electricity-sector official profile (2025 data)
  7. [S7] SENER — Mexican electricity sector development plan 2025–2039, DOF 17 Oct 2025
  8. [S8] Presidencia de México — 25 September 2025 transcript of CloudHQ announcement
  9. [S9] US EPA ENERGY STAR — Marvell Semiconductor installed air-side economizer cost and observed electricity-use comparison

Primary sources and evidence provenance

  1. CloudHQ QRO Campus presentation (branded corporate slides, September 2025, page 4; reproduced by third-party host)

    Branded slide states up to 600MW of critical computing load, initial electricity for first 200MW of 900MW campus requirement, private substation up to 900MW, proposed 2GW switching station, planned US$4.8bn construction and greater than US$250m predevelopment; hosted outside company domain, authenticity not independently established.

  2. CloudHQ / QRO Campus — company project page, accessed 22 Oct 2026

    Company describes six 48 MW IT-load buildings; separately lists 360 MW total critical IT load, RFS within 2027, 400 kV on-site substation. Descriptions may reflect distinct phasing assumptions.

  3. Presidencia de México / Secretaría de Economía — investment announcement, 25 Sep 2025

    Public announcement of prospective US$4.8 billion investment and six data centres in Querétaro; announcement does not prove cash disbursement, committed leases or operating income.

  4. El Economista — reporting on CloudHQ executive remarks, 10 Sep 2026

    Reporter attributes to CloudHQ Mexico lead a completed first 400-kV substation, second 36% progress, land and power schedule impacts. Secondary reporting, not independent technical commissioning confirmation.

  5. ODATA / Aligned Data Centers — official Querétaro announcement, 27 Feb 2025

    Different developer stated it had achieved energization milestone at its Querétaro DC QR03 campus; comparison is qualitative only, not evidence that CloudHQ has energized capacity.

  6. El Economista — attributed 900 / 920 MW campus scope and 200 MW power arrangement, 10 Sep 2026

    Executive comments reported a possible campus scale up to 920 MW; 2025 government communication referenced 900 MW and secured power for first 200 MW. Distinct scope/phase from current site IT-load figures.

  7. ODATA / Aligned Data Centers — first QR03 building launch, 30 Apr 2025

    Developer disclosed initial building 72 MW IT and up to 300 MW ultimate IT capacity; helpful comparator for the difference between launch-phase capacity and eventual site scale, not CloudHQ actual delivery.

  8. SENER — Mexican electricity sector development plan 2025–2039, DOF 17 Oct 2025

    Official Mexican power-sector planning, including forecast supply/demand outlook. Planning estimates do not certify individual interconnections or energy availability.

  9. CloudHQ Mexico investor presentation to government — September 2025 (5-page project PDF)

    2025 presentation listed up to 600 MW critical computing load, 900 MW private campus substation and 2 GW switching station, and preliminary capex assumptions; phase definitions differ from other public statements.

  10. Presidencia de México — 25 September 2025 transcript of CloudHQ announcement

    Executive remarks reference initial 200 MW power secured, 900 MW campus load and wider 2 GW switching station; speech contains a differing use of IT versus electrical load from slide materials.

  11. El Economista — 5 October 2026 CloudHQ scope and financing update

    Reports state-government meeting in which planned financing increased toward US$6 billion, and associated energy capacity from 250 MW toward 1,000 MW; this is updated announced scope, not verified deployment or spending.

  12. El Economista — CloudHQ reported expanded proposed investment, 5 October 2026

    Secondary reporting attributes update from proposed US$4.8bn to nearly US$6bn and energy infrastructure near 1,000MW; project-scale announcement, not audited invested capital or accepted supply.

  13. Proyectos México — electricity-sector official profile (2025 data)

    System-level 2025 generation, demand, network and user statistics; cannot establish spare power at the CloudHQ campus node.

  14. SENER — 2025–2039 electricity development plan, official October 2025 publication

    Published national planning and projected infrastructure reinforcement; regional milestones require current and project-specific verification.

  15. Presidencia de México — September 25, 2025 conference transcript, capacity discussion

    Official transcript includes verbal reference to around 900 MW of critical computing load, while CloudHQ-branded presentation uses 600 MW computing load and 900 MW campus electrical infrastructure; differences require validation, not forced equivalence.

  16. US EPA ENERGY STAR — Marvell Semiconductor installed air-side economizer cost and observed electricity-use comparison

    Historical observed facility electricity use and reported operational cost savings, disclosed by US EPA ENERGY STAR; independent sector precedent, not attributable to CloudHQ or LARGITAS.